background
The city of Bradford West Gillimbury has received Direct Underground Inc. DRURY Street, Mary Street, Thomas Street, Elizabeth Street and the Holland Court Reconstruction Project.
Project functions
The overall work includes sanitary sewer, minor storm channel changes in selected sanitary lateral exchange, watermainer replacement, curb and sidewalks, additional street lighting and street reconstruction.
Where and when
The construction is planned for the following streets, as described in the map.
- Holland Court
- Mary Street
- Thomas Street
- Elizabeth Street
- Drury Street
The work should begin the week of August 11thTH2025, with expected completion until December 2025. Minor restoration work may be required in spring 2026.
What you can expect before building
The work teams mark the locations of underground supply companies such as gas, water and hydro on the floor with color and/or flags.
Before the start of the work, owners should objects that are located within the limits of the city object (boulevard), including landscaping and/or decorative fences or objects before the work begins. If you have a sprinkler system in the boulevard, please contact a member of the project team (listed below).
How you can be affected
General traffic and water supply:
All roads remain open throughout the project, but there will be traffic congestion around construction zones that can lead to delays. Occasionally, we can limit access to driveways for short periods to facilitate road, sidewalk and contain construction work in front of your house. In these cases, we will work with you directly to facilitate access to your property and to offer parking.
In the event of a planned disturbance of your water supply, we will share a message at least 24 hours before the fault.
Residents within the construction area:
Waste collection
The waste collection continues as regularly. Please make sure that your house number is clearly specified on your garbage, recycling and compost container to guarantee the weekly collection and return during the entire building.
Permission to enter
The project also includes the classification and restoration of the boulevard on various properties. If your property is impaired, you will receive a separate request to give the city permission to enter your property in order to do the necessary work.
Accommodation
Residents who need accommodation (level, longer termination, etc.) must contact the city's employees (listed below) in order to arrange access during the construction period.
Park
In order to minimize the effects on the construction, the residents will do without the street on the street on the street from Monday to Friday. Please park in entrances and neighboring streets.
Contact information:
City of Bradford West Gillimbury
Jeff Sculthorp, C.Tech. ,,
Project manager, capital projects
City of Bradford West Gillimbury
3541 line 11, Bradford, on L3Z 2A8
905 775 5366 Ext. 2113
[email protected]
Lead CA/project manager
Rick David, PMP
WSP Canada
100-3050 Harvester Road
Burlington, On, L7N 3J1
289-208-2853
[email protected]